1. Executive Summary
Alongside recovery, Gary redesigned picking locations, replenishment and stock movement, introduced pick-to-zero disciplines and improved equipment and flow. A Monday-to-Friday single shift replaced continuous three-shift operation. Daily picking throughput increased from 800 to 1,600 order lines.
Recovery restored the ability to complete and release orders. Transformation established a different operating model that delivered twice the daily picking throughput within a substantially shorter working week.
2. Context and Need for Intervention
The operation generated $150 million annually through three distribution centres. Following an ERP implementation, service fell below 20% and 44,000 order lines accumulated.
Export consignments remained incomplete and major customer relationships were threatened. Technical support and three-shift, seven-day working failed to restore dependable fulfilment.
The business held $25 million of constrained inventory but could not consistently establish availability, allocate stock and complete customer orders.
3. Establishing Reality
Gary investigated physical stock, outstanding orders, system exceptions and the route from order acceptance to dispatch.
Three weaknesses emerged:
Unreliable inventory: 70% of inventory records checked were inaccurate, despite management’s assumption of 70% accuracy. There had been no comprehensive stock-take for twelve years.
Disconnected transactions and physical work: recurring system exceptions obstructed allocation and picking even when goods were available to ship.
Conflicting priorities: commercial teams competed for warehouse capacity while extended shifts and manual intervention concealed weak operating control.
Export consignments made the commercial consequence visible. Letters of credit required complete shipments without variation. Partially assembled consignments could not be dispatched, leaving stock committed to the marshalling dock, and revenue unrealized.
Inventory creates little commercial value when the organization cannot identify, allocate and deliver the combination a customer has agreed to buy.
4. Leadership and Decision Rights
Gary’s Interim COO authority extended across the operational and commercial interfaces causing the failure.
With picking capacity limited to 800 order lines a day, he required sales leaders to agree priorities and submit coordinated requirements. Inventory accuracy became an operating responsibility supported by financial oversight.
The warehouse could not resolve the problem alone. Purchasing priorities, commercial commitments and system discipline had to change together.
5. Intervention and Operating Changes
Gary organized a wall-to-wall stock-take in one operational day instead of the proposed four-day shutdown. The corrected baseline supported stronger perpetual controls and resolution of recurring transaction errors.
Item information, units of measure and handling rules were aligned with physical picking and replenishment. The team released aged customer orders and export consignments as allocation problems were resolved.
As executable orders cleared, the warehouse began running short of work it could complete despite substantial remaining stock. Gary and a colleague identified 31 critical products whose shortages blocked a significant number of orders. He redirected purchasing attention towards accelerating the acquisition of those items.
At the same time, he redesigned picking locations, replenishment and stock movement, introduced pick-to-zero disciplines and improved equipment and flow. Controlled single shift, staggered-day working replaced reliance on continuous three-shift operation.
Recovery released trapped business; the redesigned arrangements improved the ability to execute subsequent commitments.
6. Results and Transfer
The six-month intervention delivered:
Profitability: $7.5 million cumulative improvement, substantially supported by releasing trapped orders and inventory into completed, invoiced sales.
Throughput: daily picking increased from 800 to 1,600 order lines.
Service: 99% of order lines fulfilled within seven days; a separate measure recorded 95% of complete orders (QUOTIF) within five days.
Quality: customer error claims fell by 95%.
Operating capability: a Monday-to-Friday single-shift model replaced three-shift, seven-day working, supported by stronger inventory controls, coordinated purchasing priorities and redesigned warehouse processes.
Employees later reported that key arrangements remained in use for several years. Some were subsequently changed under different leadership.
Client testimonial
“Gary, the turnaround you led across our three UK distribution sites was exceptional. Quite simply, we would not have achieved the recovery in operational performance without your intervention. [The Group CEO] and I both recognise the depth and immediacy of your impact. Please know your efforts have made a lasting difference to our group performance and stability.”
Chief HR Officer, Northern Europe, international manufacturing group
7. What This Practical Example Demonstrates
Gary reconnected inventory information, commercial priorities, purchasing and physical execution. Immediate recovery and operating redesign reinforced one another.
The decisive shift was from working harder around constraints to removing the constraints preventing customer commitments from becoming completed sales.
Intervention Pathway: RPR to OMT, with overlapping recovery and transformation.Delivery Model: Gary-led recovery, design and implementation under Interim COO authority.